5Cs Joint Committee

 

 

Report of the Client Relationship Director

Author:  Matt Goodwin

Telephone: 07771 378362

E-mail: matt.goodwin@havant.gov.uk

 

To: The Members of the 5Cs Joint Committee

DATE: 6 October 2021

 

 

 

 

Capita Performance Report, to August 2021

Recommendation(s)

a)    To note the performance reported against contract measures.

b)    To direct interventions or further investigations regarding performance, as considered necessary.

 


Purpose of Report

1.    This report presents the summary of performance across all services within the Capita contract from the month of January 2021 to August 2021. Commentary focuses on the period June 2021 to August 2021.

Background

2.    Performance of the Capita contract is monitored at least monthly through the performance measures set out in the contract; these measures are a range of Key Performance Indicators and Performance Indicators. 

3.    The purpose of this report is to provide Members of the Joint Committee with the current performance status of the contract.  It also details the current status of rectification activity, and progress made against those rectification plans.

4.    The report covers the period from the month of January 2021 to August 2021, with data supplied as per Appendix A. Some of the more variable Customer Services data is shown in graph form in Appendix B, to better illustrate trends. Definitions of performance indicators can be found in Appendix C.

5.    The commentary below relates only to the exceptions and further details can be found in Appendix A and within each individual performance tile on the Socrata system.

SERVICE LEVEL COMMENTARY

LAND CHARGES

6.    Land Charges met all its performance measures. This is in the context of impacts caused by the changing Government stance on Stamp Duty and new working styles under the pandemic.

CUSTOMER SERVICES

7.    The performance picture for Customer Services remains complex. Failures under PI 002 have continued, due to an unprecedented increase in the number of calls related to waste collections for Havant Borough Council. The Authority have continued to press for a joint resolution to issues in this area and have made significant progress in matters such as communications. This is providing for a stronger customer experience which, certainly in July and August, has seen a reduction in call volumes from a significant peak in June 2021. This continues to be closely monitored and specific interventions in areas such as complaints resolution are being rolled out.

8.    Linked to the above, a failure of KPI 004 was also triggered. This is a quarterly KPI covering % of customer satisfaction assessed through a Customer Services agent led question set. This performance was clearly linked to dissatisfaction relating to waste calls for Havant Borough Council. The expectation is that the picture will improve if there is a turnaround on Waste Calls. However, wider work on assessing customer satisfaction is underway with Capita.

9.    On the Revenues and Benefits lines, covered under PI 004, there had been serial failures on monthly call handling performance during 2020, and early in 2021.  Following implementation of an agreed Service Improvement Plan, there have been improvements over recent months, with the PI achieved between April and July 2021. In August, there was a PI failure realised, due to increases in call volumes arising from distinct post Covid-19 recovery actions requested by Authorities. These include re-instigation of Council Tax reminders and court action, where this had previously been paused.

IT

10. IT met all of its performance measures.

REVENUES & BENEFITS

11. Revenues & Benefits performance indicators are reported on annually, in May to June 2021. The report presented to an informal meeting of members of the Committee in July 2021 covered this position.


 

RECTIFICATION PLANS

12.As at the time of this report, the following rectification plans remain open:

Ref.

Area

Default

Update

RP1-2020

Finance and Exchequer

VAT Coding Errors

The rectification activity within this plan has been delivered.  Closure of the plan has been paused pending HMRC feedback on issues for Havant and East Hampshire.

RP4-2020

Revenues and Benefits

Management of Committals / Summonses for South and Vale

Rectification activity within this plan has been delivered, with regards to ensuring processes operate correctly now. The implications of past issues remain under consideration.

 

13.One plan has been closed since the last meeting:

Ref.

Area

Default

Update

N/A

Finance and Exchequer

PI 004 Statement of Accounts

Superseded by return of Finance and Accountancy Service.

 

This had been kept open pending resolution of a request for compensation for additional audit fees incurred by Authorities. This has been resolved.

 

Climate and ecological impact implications

14. No specific impacts.

Financial Implications

15. There are no direct financial implications arising from this report. 

Legal Implications

16. There are no direct legal implications arising from this report.

Risks

17. There are no material risks arising directly from this report.

Other Implications

18. There are no direct equalities implications arising from this report.

Conclusion

19. The following recommendations are tabled to the Committee:

a)    To note the performance reported against contract measures.

b)    To direct interventions or further investigations regarding performance, as considered necessary.

Background Papers

·        None supplied.

 


 


Appendix A: Performance Information

 


 


Appendix B – Trend Graphs for Customer Services Measures

 

 



Appendix C - Performance definitions

 

Customer Services

KPI002

Maintain first time resolution – Revenues and Benefits Customer Contact above 80% through September 2025

KPI003

Maintain first time resolution – Contact Centre/Switchboard – above 95% through September 2025

KPI004

Maintain Customer satisfaction above 95% through September 2025

PI001

Maintain emails responded to by the close of the next working day above 95% through September 2025

PI002

Maintain % of calls answered in 20 seconds across the Contact Centre above 80% through September 2025

PI003

Maintain % of hour of hours calls answered in 50 seconds above 80% through September 2025

PI004

Maintain % of council tax and benefits related calls answered in 60 seconds above 80% through September 2025

PI005

Maintain % of visitors with appointments for in-scope services to be seen within 2 minutes at Customer Access points / Remote Offices above 80% through September 2025

 

Land Charges

PI002

Maintain local land charges registrations completed within 24 hours of receipt above 99% through September 2025

PI003

Maintain complaints upheld relating to search below 0 complaints through September 2025

KPI001

Maintain % of all official and accepted requests for local authority searches returned within 5 working days of receipt above 50% through September 2025

PI001

Maintain % of all official and accepted requests for local authority searches returned within 8 working days of receipt above 99.5% through December 2025

 

 

 

 

 

 

 

 

 

Revenues and Benefits

 

KPI001

 

Maintain average speed of processing for new benefits claims below 13 Days through September 2025

KPI002

 

Maintain average speed of processing for benefit changes on or below 6 Days through September 2025

PI001

 

Maintain financial accuracy of benefits assessments above 96 % through September 2025

PI002

 

Maintain council tax in year collection above targeted % through March 2021

PI004

 

Maintain council tax in year collection above targeted % through March 2021

PI 005

 

Maintain business rates in year collection above 99 % through September 2025

PI 007

 

Maintain housing subsidy claims accurately completed & submitted on a timely basis above 100 % through September 2025

 

 

IT

KPI01

Maintain availability of internal facing business critical services above 99.9% through September 2025

KPI02

Maintain availability of external facing business critical services for core hours above 99.9% through September 2025

KPI03

Maintain availability of external facing business critical services for non-core hours above 99% through September 2025

KPI04

Maintain incident management - P1 (severity 1 service incident) above 90% through September 2025

PI001

Maintain patch management above 90% through September 2025

PI003

Maintain incident management of severity 2 - severity 4 service incidents above 90% through September 2025

PI004

Maintain service requests above 90% through September 2025

PI005

Maintain change requests above 90% through September 2025

PI006

Maintain first time fixes above 60% through September 2025